Construction management for the Blast Furnace 6 Revamp Project. Responsible for the dust removal installation, hydraulics and furnace houses including furnace house machinery. Safely and successfully completed in March 2024.
Project Description
On behalf of Tata Steel, we provided construction management for the Blast Furnace 6 Revamp Project. This was an intensive and challenging job where we focused on multiple key components of the blast furnace.
- Construction management for the dust removal installation, hydraulic systems, furnace houses including furnace house machinery
- Placement of the Hoods Above Taphole (Forge hoods) for significant emission reduction during open drilling and closing of the taphole for molten iron
- Completed without significant incidents. Safety always came first!
The project was successfully and to the correct quality standards completed in March 2024.